An esteemed offshore fleet operator approached GLO MARINE with a challenging yet critical project. The task was to conduct a detailed survey, 3D scanning, and engineering for three Offshore Supply Vessels (OSVs) from their fleet of six.
This project was not just about precision and technical expertise but also about the efficiency of execution within a demanding timeframe.
The project’s main challenge was the limited space within the engine rooms, demanding precise integration of new equipment without disrupting existing systems. Additionally, the project required simultaneous surveys and scans across all three vessels, adding layers of complexity to our task.
Compounding these challenges was the ambitious deadline: completing the entire engineering and design process for all three vessels within a mere 6 weeks. This required exceptional project management and efficient execution from our team.
Dedicated field service teams deployed to remote location in Indonesia where ships were berthed for other retrofitting jobs and performed 3D scans of engine room and survey for all 3 vessels in just 3 days.
The whole process of the ballast water treatment system integration was completed in an excellent timeframe of one month, as demanded by the client, in order not to have even a day of downtime.
As a result of the accuracy of the scanning and the excellent collaboration between the planning and engineering departments, the project was executed millimeter level accuracy.